Great Lakes Fishery and Ecosystem Restoration Program
USACE

Great Lakes Fishery Commission

Ongoing Projects: FRANKENMUTH DAM

Fish Passage (Frankenmuth, MI)

Project Description Frankenmuth Dam

The Frankenmuth Dam is located on the Cass River within the city of Frankenmuth, approximately 20 miles south of Lake Huron’s Saginaw Bay. The Cass River originates in Tuscola County in east central Michigan near Cass City. The Cass River’s watershed encompasses 848 sq. miles and lies within the Saginaw Bay watershed. The Frankenmuth Dam is a concrete dam, and is approximately 240 feet long with a structural height of 14 feet. It was built in the 1850s to supply water to a local mill. Although the walleye and lake sturgeon are the species targeted by the Michigan Department of Natural Resources (MDNR) and the Partnership for the Saginaw Bay Watershed, a fish passage at the Frankenmuth Dam would also increase habitat connectivity for a variety of other species including white sucker (Catostomus commersoni), white bass (Morone chrysops), smallmouth bass (Micropterus dolomieu), channel catfish (Icatalus punctatus), northern pike (Esox lucius), and steelhead (Oncorhynchus mykiss). Connecting river habitat for these species would benefit the overall diversity of Cass River and Saginaw Bay watershed species.

Nonfederal Project Sponsor

City of Frankenmuth, Michigan.

Congressional Interest

  • Senator Carl Levin (D-MI)
  • Senator Debbie Stabenow (D-MI)
  • Representative Dale Kildee (D-MI-5)

Stage

Feasibility.

Current Status

A preliminary restoration plan has been approved and a concept design completed. Future funds will be used to continue feasibility-level planning and design efforts focusing on environmental regulatory agency coordination and site data acquisition. Additional funding would be used to complete the feasibility efforts, including hydraulic modeling, detailed design, feasibility report preparation, and administrative review and approval.

Funding

Total Federal Nonfederal
Current working estimate $2,400,000 $1,560,000 $840,000
Funding to date $125,400 $125,400 $0
Funds required to complete project $2,274,600 $1,434,600 $840,000
 

 

Frankenmuth Dam Project Manager

Patrick Kuhne
(313) 226-6767
patrick.a.kuhne@usace.army.mil

Click here to download a copy
of this project summary sheet.